A question that has been asked by multiple community members recently is:
"When I change the end data of a task, how can I have that change automatically update the start and end date of dependent tasks, while also maintaining the original duration of the dependent task?"
Jira Cloud does not do this inherently, but it can be done with limitations using Automation for Jira.